Marmaris Boutique Hotel — Foundation Pour
Client
Mavi İnşaat Ltd.
Location
Marmaris, Muğla
Year
2024
Category
beton-pompasi
Case Study
Our approach and execution
1,850 m³ of concrete delivered in a single stage through 14 hours of continuous pouring with Schwing S58.
Due to the requirement for a monolithic (single-pour) hotel foundation, the Schwing S58 SX unit with 58-metre boom length was allocated. Road closure and mixer rotation planning were coordinated by our company.