Fethiye Marina Residence — Steel Construction Assembly
Client
Akdeniz Yapı A.Ş.
Location
Fethiye, Muğla
Year
2024
Category
mobil-vinc
Case Study
Our approach and execution
Total 320-tonne steel panel assembly using a 130-tonne mobile crane on a 14-storey coastal-belt project.
Within the scope of the 4-month project conducted with the Liebherr LTM 1130-5.1 unit, drone-supported rigging plans were prepared for each panel. Due to the site's 35-metre distance from the shoreline, the wind profile was continuously monitored and the operation schedule was dynamically updated based on wind data.